To consider the report of the Director (J-PH).

 

Decision:

Agreed

RECOMMENDED that Council approve of a budget of up to £200,000 in total for the project to be completed. The budget and associated work will be overseen by the Corporate Property Assets team.

 

Reason for Decision:

As set out in the report.

 

 

 

 

Minutes:

The Executive considered the report for additional funding for the Queen Street lift at Royal Albert Memorial Museum (RAMM), following a recent procurement process. The replacement of the lift would support residents with mobility issues and for pushchairs to gain access to the museum.

 