The Chairman welcomed everyone present to first meeting of the Executive Committee. 

 

There were no questions from members of the public.

2.

Declarations of Interest

Minutes:

There were none.

3.

Confidential/exempt items – there are two items which officers recommend should be dealt with in this way.

Minutes:

RESOLVED:

that the classification given to the documents submitted to the Executive Committee be confirmed; there were two items which officers recommended should be dealt with in Part B

4.

Arrangements for Governance, operation and stakeholder interaction pdf icon PDF 738 KB

Habitat Regulations Delivery Officer

The  report sets out the Governance arrangements and method of operation for the Habitat Regulations Executive Committee (HREC) as agreed by East Devon District Council, Exeter City Council and Teignbridge District Council.

Additional documents:

Minutes:

The Executive Committee considered the Habitat Regulations Delivery Officer’s report setting out the governance arrangements and method of operation for the South East Devon Habitat Regulations Executive Committee (HREC), as agreed by East Devon District Council, Exeter City Council and Teignbridge District Council.  The report also detailed the working relationships between the HREC, the Habitat Regulations Delivery Officer, the Officer Working Group and the Green Infrastructure (GI) Board.

 

The HREC was responsible for overseeing the habitat mitigation delivery required by the South East Devon European Mitigation Strategy, endorsed by all three authorities, to ensure that development within each authority’s Local Plans could proceed.

 

In response to a suggestion put forward to include the word ‘provisionally’ in there commendations, the Strategic Lead – Legal, Democratic Services and Licensing advised that certain decisions had to be agreed by the Executive Committee in order to proceed with the work detailed within the Annual Business Plan and 5 Year Delivery Programme.

 

RESOLVED: that the South East Devon Habitat Regulations Executive Committee:

 

1. Endorses the South East Devon European Site Mitigation Strategy, noting that:

ØFurther work is required to confirm overall SANGS requirements;

ØThe need for future re-evaluation of the (Table 26) costs therein, in particular SANGS delivery priorities and associated costs; and,

ØThe need for future re-evaluation of approaches to securing funds for SANGS delivery through CIL and Section 106, taking account of any forthcomingamendments to the CIL regulations.

 

2. Notes the Terms of Reference and Rules of Procedure which govern the running of the HREC and which have been agreed by the three authorities and that the Committee has no authority in respect of Compulsory Purchase powers.

 

3. Notes the intended working relationships between all interested parties.

 

4. Agrees to using East Devon District Council’s Contract Standing Orders and financial rules (adapted to suit as appropriate by East Devon District Council’sStrategic Lead for Legal, Licensing and Democratic Services and S.151 Officer)for all procurement until such time as the HREC agrees its own procurementrules.

 

5. Delegates all necessary powers to the Delivery Officer to enable the delivery and implementation of approved mitigation projects (including the hiring of staff,purchasing vehicles and equipment, awarding monitoring and surveyingcontracts) with any expenditure being identified in the Annual Business Plan or 5yr delivery programme and limited to a maximum sum of £50,000 per item. Thisdelegated authority shall not include decisions relating to:

a. Agreeing the Annual Business Plan and 5 yr delivery programme.

b. Any expenditure not contained within the approved Business Plans.

5.

Financial report pdf icon PDF 316 KB

Habitat Regulations Delivery Officer

The report seeks to update members of the Executive Committee on the overall financial position regarding mitigation payments towards projects identified in the South East Devon European Site Mitigation Strategy (SEDESMS).

Minutes:

Financial report

The Executive Committee considered the Habitat Regulations Delivery Officer’s report updating Members on the overall financial position of developer contributions received by all three local authorities as mitigation payments toward measures identified in the South East Devon European Site Mitigation Strategy. The report also included anticipated income from contributions where planning permission had been granted, however the mitigation payment had not yet been paid. 

 

RESOLVED: that the South East Devon Habitat Regulations Executive Committee:

 

1. Notes the progress made in collating detailed financial information from the three authorities.

 

2. Receives quarterly updates on the overall financial position including contributions received, contributions not received because arrangements may be in place for contributions to be with-held, expenditure and anticipated contributions (from signed S106).

 

3. Receives *annual updates on 5 year income forecasts of developer contribution receipts, clearly identifying where these have been retained by the collecting authority where any agreement is in place for contributions to be with-held.

 

4. Agrees that, as financial administrator, EDDC will invoice Exeter City Council and Teignbridge District Council quarterly in arrears, as a minimum, to cover agreed costs incurred by EDDC on behalf of the Partnership.  An exercise to agree balances between the parties will also be initiated quarterly by EDDC.

 

(* - see resolution 5 of minute 6 re arrangements for more frequent reporting in the first 12 18 months)

6.

Annual business plan and Five year delivery programme pdf icon PDF 135 KB

Habitat Regulations Delivery Officer

The report sets out the principles for the on-site projects which have been recommended as a priority by the Habitat Regulations Delivery Officer, in conjunction with the Officer Working Group. These projects are contained within Annual Business Plan (appendix 1) and the 5Yr Delivery Programme (appendix 2) which the Executive Committee is asked to approve.

Additional documents:

Minutes:

Annual Business Plan and Five-Year Delivery Programme

The Executive Committee considered the Habitat Regulations Delivery Officer’s report setting out the principles for the on-site projects, which were recommended as a priority by the Delivery Officer, in conjunction with the Officer Working Group. The projects were detailed within the Annual Business Plan and Five Year Delivery Programme, which were both appended to the Committee report.

 

During discussion, it was proposed that the role of the Habitat Regulations Delivery Officer should be included in the next Annual Business Plan and 5 Year Delivery Programme. The contract for the post was currently scheduled to end in spring 2018 and it was considered that this should be reviewed to ensure delivery of the Programme.

 

In response to comments made regarding potential impacts from the outcome of recent the European Union referendum, Amanda Newsome (Natural England) advised that at present there was no change in the law or policy protecting wildlife. All of the EU Directives, which related to wildlife protection, had been transposed into UK law and it would require new

Acts of Parliament to revoke any of it. Concern was raised by Members that the outcome could result in a ‘slow-down’ in the development industry and therefore there would be value in having more frequent updates on development forecasts Notwithstanding resolution 3 in minute 5, in light of concerns over impact of the referendum results more regular reporting on developer forecasts was felt appropriate.

 

RESOLVED: that the South East Devon Habitat Regulations Executive Committee:

 

1. Approves the 2016 Annual Business Plan appended to the committee report and commitments and actions set out therein.

 

2. Approves the 5 Year Delivery Programme appended to the committee report.

 

3. Receives a progress update on the delivery of the Annual Business Plan at the next meeting (quarterly basis).

 

4. Agrees that the Habitat Regulations Delivery Officer role be included in the next Annual Business Plan and 5 Year Delivery Programme.

 

5. Receives an update on development forecasts every six months for the next 12-18 months.

7.

Dawlish Warren Visitor Centre pdf icon PDF 172 KB

Habitat Regulations Delivery Officer

The report details an opportunity to deliver a new visitor centre at Dawlish Warren.

Additional documents:

Minutes:

The Executive Committee considered the Habitat Regulations Delivery Officer’s report outlining an opportunity to deliver a new visitor centre at Dawlish Warren. Members noted that the project was identified through the South East Devon European Site Mitigation Strategy and that significant match funding might be available for a limited period.

 

RESOLVED: that the South East Devon Habitat Regulations Executive Committee:

 

1. Agrees the principle of prioritising a further £220,000 of Partnership funds as a contribution towards the replacement Dawlish Warren visitor centre in 2019/20,subject to sufficient monies being available.

 

2. Agrees the redirection of the £220,000 of Partnership funds to other projects if sufficient match funding to take the Dawlish Warren Visitor Centre project forward is not secured by June 2019.

8.

Joint Communications Strategy pdf icon PDF 75 KB

Habitat Regulations Delivery Officer

The reports sets out the Habitat Regulations Mitigation Communications Protocol, which seeks to ensure that the work of the Committee is communicated positively and enable the project to be promoted in a consistent and coordinated manner, internally and externally.

Additional documents:

Minutes:

The Executive Committee considered the Habitat Regulations Delivery Officer’s report seeking approval of a communication protocol to ensure that the reputations of the Executive Committee and the respective Councils were protected. It also would also ensure that the work of the Executive Committee was communicated positively and adverse publicity was avoided or limited. Key communication messages, which had been written to enable the work of the Executive Committee to be promoted in a consistent and coordinated manner, internally and externally, were also noted.

 

In response to a comment about the need to promote a clear message about the benefits of the works being progressed in respect of delivering the Mitigation Strategy, it was advised that a press-release on the outcomes of the Executive Committee’s first meeting would be published by the Growth Point’s Communications Officer within the next couple of weeks. The importance of communication being in plain English was highlighted.

 

 

RESOLVED: that South East Devon Habitat Regulations Executive Committee:

 

1. Approves the Habitat Regulations Mitigation Communications Protocol as set out in appendix 1 to the committee report.

 

2. Note the key communications messages as set out in appendix 2 to the committee report.

9.

Forward Plan and programme of meetings

Strategic Lead – Legal, Democratic Services and Licensing and Monitoring Officer

Minutes:

The Strategic Lead – Legal, Democratic Services and Licensing asked Members to agree the proposed dates for future meeting of the Executive Committee. A Forward Plan of key decisions would be published at least 28 days prior to each meeting as set out in the Executive Committee’s Terms of Reference. 

 

RESOLVED: that dates proposed for future South East Devon Habitat Regulations Executive Committee meetings be agreed.

 

Ø21 September 2016

Ø18 January 2017

Ø 29 March 2017

10.

Exclusion of the public

Minutes:

RESOLVED: that under Section 100(A) (4) of the Local Government Act 1972 the public (including the press) be excluded from the meeting as exempt information, of the description set out on the agenda, is likely to be disclosed and on balance the public interest is in discussing this item in private session (Part B).

Chairman made to move then following

11.

Suitable Alternative Natural Green Space (SANGS) – Introduction and Options under investigation

Minutes:

The Executive Committee considered the Habitat Regulations Delivery Officer’s report outlining the concept of Sustainable Alternative Natural Green Space (SANGS) and options for sites currently under investigation across the three local authority areas.

 

The creation of alternative sites (SANGS) sought to divert visitors away from sensitive European sites and was being promoted as a mitigation measure, one of many, to ensure no adverse effect on the integrity of the European Sites as a result of new development.

 

RESOLVED: that the South East Devon Habitat Regulations Executive Committee notes the progress towards delivering SANGS options across the region.

12.

Suitable Alternative Natural Green Space (SANGS) – Opportunity

Reasons for consideration in Part B: Para 3 Schedule 12A Information relating to the finance or business affairs of any particular person

Minutes:

The Executive Committee considered the Habitat Regulation Delivery Officer’s report advising Members of an opportunity to acquire land for SANGS; this would be forward funded and would play a key role in mitigating the impacts of development within the three local authority areas.

 

The Executive Committee discussed the challenges in respect of delivering SANGS sites and the need to look at each individual opportunity on its own merits.  

 

RESOLVED: that the South East Devon Habitat Regulations Executive Committee:

 

1. Acknowledges a request to approve the purchase of specified land Sustainable Alternative Natural Green Space (SANGS); the purchase to be forward funded;

 

2. Approves the principle of funding the purchase and instatement of the Land forSANG provision at a cost of up to the amount contained in the confidentialcommittee report, subject to conditions included in the report in respect ofacquiring the land and the Committee being satisfied with the financial budgetdetails;

 

3. Approves the use of Section 106 funding from specified development as a contribution toward the costs of the proposed SANGS on the Land;

 

4. Notes that a decision on the specific mechanism for any partnership funding and the method by which the forward funding is recouped be taken at the next committee meeting in September 2016.