Decision details

Strata Budget Monitoring Out-turn Report 2016/17

Decision Maker: Strata Joint Executive Committee

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

Agreed

 

 

that the report be noted;

 

the Board submit a report on compensation penalties for non-delivery of projects on time; and

 

that it is recommended to the three Councils to approve the appointment of two Project Managers and one Supplier Engagement Manager on fixed term contracts for 2 years.  The cost is estimated at £132,000 a year, with the balance of funding coming from anticipated additional savings generated by the Supplier Engagement Manager.

 

Reason for Decision:

 

As set out in the report

 

 

 

 

Publication date: 21/06/2017

Date of decision: 20/06/2017

Decided at meeting: 20/06/2017 - Strata Joint Executive Committee