Decision Maker: Executive, Council
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
To consider the 2023/24 HRA Budget Monitoring
Report – Outturn
Agreed:
RECOMMENDED that Council notes and approves:-
1) the supplementary budget of £50,000 as detailed in paragraph 8.5 of the report;
2) the HRA financial position for 2023/24 financial year;
3) the revision of the HRA Capital Programme to reflect the reported variations detailed in Appendix 3 of the report;
4) the request to transfer £466,000 from the social housing acquisitions Section 106 budget to the social housing acquisitions open market budget as detailed in paragraph 8.13 of the report;
5) to request £74,000 of additional funding to finalise the Hamlin Gardens project; and
6) to request that the new HRA development at Hamlin Gardens (Brooke House) be designated as a scheme for applicants over the age of 60, as detailed in paragraph 8.14 of the report.
Reason for Decision: As set out in the report.
Report author: David Hodgson
Publication date: 10/07/2024
Date of decision: 09/07/2024
Decided at meeting: 09/07/2024 - Executive