Issue - meetings

Capital Monitoring Statement

Meeting: 01/10/2013 - Executive (Item 97)

97 Capital Monitoring Statement to 30 June 2013 pdf icon PDF 85 KB

To consider the report of the Acting Assistant Director Finance.

Scrutiny Committee – Resources considered the report at its meeting on 18 September 2013 and its comments will be reported.

(Report circulated)

 

Additional documents:

Decision:

The report of the Acting Assistant Director Finance was submitted, reporting on the current position in respect of the Council’s revised annual capital programme and advising Members of the anticipated level of deferred expenditure into future years.

 

Members were asked to approve an urgent request for an additional sum of £36,000 to complete essential resurfacing of Leighton Terrace car park. The works were necessary to ensure that the car park could continue to operate and comply with Health and Safety Regulations.

 

The Deputy Chief Executive claified that, as a result of this valuation, the Council had updated its estimates process.

 

Members discussed the wider issue of the tendering and procurement process within the City Council and the need to ensure that small local businesses were not precluded from tendering for Council Projects. The Chair suggested that the tendering and procurement process could be an issue for Scrutiny Committee – Resources to scrutinise.

 

The Portfolio Holder for Housing and Customer Access expressed disappointment that the scheme to help bring empty properties back into use had been withdrawn due to lack of interest from landlords. The Acting Assistant Director Finance would clarify if these funds would have to be given back to the Government.

 

The Portfolio Holder for Economy and Culture advised that the scheme to replace the running track at Exeter Arena had been deferred to take account of the weather conditions required for works to be undertaken.

 

Scrutiny Committee – Resources considered the report at its meeting on 18 September and the comments of the Members were noted.

 

Executive recommended that Council notes and approves the current position in respect of the annual capital programme and requested to approve an urgent request for an additional £36,000 to complete the resurfacing of Leighton Terrace car park.

 

Minutes:

The report of the Acting Assistant Director Finance was submitted, reporting on the current position in respect of the Council’s revised annual capital programme and advising Members of the anticipated level of deferred expenditure into future years.

 

Members were asked to approve an urgent request for an additional sum of £36,000 to complete essential resurfacing of Leighton Terrace car park. The works were necessary to ensure that the car park could continue to operate and comply with Health and Safety Regulations.

 

The Deputy Chief Executive claified that, as a result of this valuation, the Council had updated its estimates process.

 

Members discussed the wider issue of the tendering and procurement process within the City Council and the need to ensure that small local businesses were not precluded from tendering for Council Projects. The Chair suggested that the tendering and procurement process could be an issue for Scrutiny Committee – Resources to scrutinise.

 

The Portfolio Holder for Housing and Customer Access expressed disappointment that the scheme to help bring empty properties back into use had been withdrawn due to lack of interest from landlords. The Acting Assistant Director Finance would clarify if these funds would have to be given back to the Government.

 

The Portfolio Holder for Economy and Culture advised that the scheme to replace the running track at Exeter Arena had been deferred to take account of the weather conditions required for works to be undertaken.

 

Scrutiny Committee – Resources considered the report at its meeting on 18 September and the comments of the Members were noted.

 

RECOMMENDED that Council notes and approves the current position in respect of the annual capital programme and requested to approve an urgent request for an additional £36,000 to complete the resurfacing of Leighton Terrace car park.

 

(Report circulated)


Meeting: 18/09/2013 - Scrutiny Committee - Resources (Item 37)

37 Capital Monitoring Statement pdf icon PDF 85 KB

To consider the report of the Acting Assistant Director Finance – report circulated

Additional documents:

Minutes:

The Acting Assistant Director Finance presented the report, advising the current position in respect of the Council’s revised annual capital programme and of the anticipated level of deferred expenditure into future years.

 

Members were asked to support the approval of an urgent request to the Executive for of an additional sum of £36,000, to complete essential resurfacing of Leighton Terrace car park.  The works were considered necessary to ensure that the car park could continue to be operated in a safe manner and avoid any temporary closure. The Deputy Chief Executive explained that an evaluation had been based on supplied information; he would investigate and circulate a reply to Members. A more proactive planned approach to commercial property maintenance would be taken.  A Member referred to the uneven surface of the car park at the Exeter Arena Athletics Stadium and was currently awaiting a reply to her enquiry on this issue. The Acting Assistant Director Finance clarified that £71,000 available funding would be used for specific national cycle network projects, with the City Council carrying out the work on behalf of the County Council.  He would send a breakdown of expenditure on the anticipated projects.

 

Scrutiny Committee – Resources noted the current position and recommended approval by Council of the revised annual Capital Programme, and an urgent request for an additional £36,000 to complete the resurfacing of Leighton Terrace car park.

 