Items
| No. |
Item |
84. |
Apologies
To receive apologies for absence from
Committee Members.
Minutes:
Apologies were received from
Councillors Mitchell, Banyard and Atkinson.
Apologies were also received
from the Chief Executive.
|
85. |
Minutes PDF 323 KB
To approve and sign the minutes of the meeting
held on 4 September 2025.
Minutes:
The
minutes of the meeting held 4 September 2025 were taken as read,
approved and signed by the Chair as correct.
|
86. |
Declarations of Interest
Minutes:
No declarations of disclosable
pecuniary interests were made.
|
87. |
Review of Corporate Governance Risk Register
To hear an update on
work on the new risk register in line with the new corporate plan,
including expert information from Zurich Resilience
Solutions.
Minutes:
The Chair advised that this item
would be heard first.
The Strategic Director for Corporate Services
introduced the report advising Members that work had been
carried out with Zurich to strengthen the Council’s approach
to risk and the Risk Register, and to ensure the updated Corporate
Risk Register was inline with the new Corporate
Plan.
The Principal Risk Consultant from Zurich Risk
Engineering UK gave a presentation to the committee, making the
following points:
- he had been working with Exeter City
Council for 2 years;
- training had been delivered to
officers and senior officers;
- risks were not just a list
of bad things, but should be meaningful and
targeted;
- risk management
supported objectives and decision
making;
- it helped to protect reputation,
finances, and confidence;
- risk was negative by nature, but
when done well it could encourage innovation;
- risk identification was the most
important part and when done correctly it could make the rest
easier;
- management of risk should sit with
officers;
- officers
should maintain the Risk Register, and Members should
make sure it linked to priorities;
- it was important to report emerging
risks and keep accountability;
- information about risks needed
detail to enable proper scrutiny;
- risks should be owned by an
individual, and they should be able to provide necessary
information about the risks;
- there were some elements of risk
that must be accepted and some higher-level risks needed to be
tolerated;
- risks that never changed were
business as usual and were therefore not really risks and could
lead to missing genuine risks;
- the Risk Register was necessary, but
the conversation surrounding it was important; and
- it was vital to ensure openness and
transparency within risk reporting;
The Strategic Director for Corporate Resources
and the Principal Risk Consultant responded to Members’
questions in the following terms:
- the different functions of
the Executive and Councillors was dependent on the
organisation;
- directorate leads and Heads of
Service take ownership of the Risk Register for their own
services;
- the Risk Register would be brought
to the Audit and Governance Committee in March
2026;
- 6 of the 13 Heads of Service had had
their management team doing risk training on specific to
service risks; and
- finance was always on the risk
register and now the risks were being looked
at to establish options for
mitigation.
It was agreed that the presentation would be
shared with the minutes.
The Audit and Governance Committee noted the
Review of Corporate Governance Risk Register report.
|
88. |
External Audit Progress Report PDF 969 KB
To consider the report of the Council’s
External Auditor.
Minutes:
The Audit Manager, Grant
Thornton presented the progress report making the following
points:
- the findings report
would not come until February;
- they were working
closely with the Strategic Director for Corporate Resources, the
Head of Service – Finance, and the Accountancy Services
Manager;
- the ultimate timeline
was the backstop date, but a buffer would be built into the
process;
- the Value for Money
work was completed and would be reported in the next item;
and
- they were on track to
deliver the Audit Findings Report and the Auditors Report on
time.
The Strategic Director for
Corporate Resources responded to Councillor Palmer by advising that
there had been a delay due to a new asset
valuation contract that had begun there was now a dedicated
officer liaising and there was a much clearer
agreement.
The Audit and Governance
Committee noted the External Audit Progress Report
|
89. |
External Auditor's Annual Report PDF 953 KB
To consider the report of the Council’s
External Auditor.
Minutes:
The Audit Manager, Grant
Thornton presented the progress report making the following
points:
- there was a new
requirement to bring the report before the end of
November;
- they
had identified three key recommendations, but these were
continuations from prior findings;
- there had been no
evidence of any further training on the counter-fraud
arrangements;
- recommendations regarding performance reporting had
been responded to by the Council, but were yet to be embedded;
and
- progress was being
made regarding the recommendations for procurement,
however there was no contract management training in
place.
The Audit Manager, Grant
Thornton, the Strategic Director for Corporate Resources, Head of
Service – Finance, and the Procurement Manager responded to
Members’ questions in the following
terms:
- recommendations and
responses from the Strategic Management Board could be found on
page 65;
- counter-fraud used to
be run by internal audit, however,
following our management restructure this took time to
put in place;
- there had been a
series of counter-fraud procedures put in place across key risk
areas;
- the forward
arrangements remained robust but there would be a meeting with the
internal auditor soon; and
- there would be an
updated counter-fraud strategy coming to the Audit and Governance
Committee next march.
- training staff had
been a priority for procurement and 145 members of staff had had
procurement training to date;
- the procurement team
had adopted a strategy, but this would be reviewed later
on;
- free Cabinet Office
contract management training would be implemented in the
future;
- there was no risk of
statutory recommendations due to the great work of the
procurement team; and
- the External
Auditor’s Annual Report was backdated work to March 2025
rather than the 25/26 financial year.
The Audit and Governance
Committee noted the External Auditor’s Annual
Report.
|
90. |
Internal Audit Progress Report PDF 190 KB
To consider the report of the Assistant
Director, SWAP.
Additional documents:
Minutes:
The Assistant Director, SWAP
presented the report for the second quarter of 2025/26 making the
following points:
- 36% of the plan had
been completed or was currently in
progress;
- there had been one
limited assurance report, which would be discussed in further
detail in the next item;
- 96 active green
actions had been identified, and 30 were overdue. In the
September meeting there were 106 active green actions with 4
overdue; and
- social housing
decarbonisation had been brought back into
plan.
The Assistant Director, SWAP
and the Strategic Director for Corporate Resources responded to
Members’ questions in the following
terms:
- SWAP were extremely experienced, and were confident
that the plan would be completed by the end of the
year;
- it was up to
management to implement the actions, SWAP were able to
follow up when completed;
- work was close to
agreement regarding the CIL
review;
- the concern of
Members regarding the response to St James Community
Trust had been noted, and a timeframe would
be sought.
The Audit and Governance
Committee noted the Internal Audit Progress
Report.
|
91. |
Limited Assurance Report PDF 246 KB
To consider the report of the Strategic
Director for Corporate Resources.
Additional documents:
Minutes:
The Head of Service –
Finance presented the Limited Assurance Report and advised the
Committee that there had been one Limited Assurance audit report on
Community Safety and Antisocial Behaviour.
The Head of Service –
Finance, Head of Service – City Centre and Net Zero, and the
Strategic Director for Corporate Resources responded to
Members’ questions in the following terms:
- the audit had been
carried out over the summer; and
- there would be a
review of the Community Safety Partnership and this was on track to
be completed by January 2026.
The Committee were advised that
the actions would be fed back to the Committee, and would also be
included in the SWAP quarterly update.
The Audit and Governance
Committee noted the Limited Assurance Report.
|
92. |
Strata DAP Internal Audit ICT Annual Report 2024/25 PDF 684 KB
To receive the report of Devon Audit
Partnership.
Minutes:
The Head of Devon Assurance
Partnership (DAP) and Chief Internal Auditor presented the report
making the following points:
- the overall assurance
opinion was reasonable assurance;
- views had been fed in
from East Devon District Councils, Teignbridge District Council,
and Exeter City Council;
- there was good
trajectory around the work that Strata were doing and they had had a new Director of
IT and Digital Transformation for the last 2
years;
- it would be
beneficial to draw attention to the aspects of delivery that were
still within the Council’s remit; and
- this was a
positive report and the
recommendations had been taken on board.
The Audit and Governance
Committee noted the Strata DAP Internal Audit ICT Annual Report
2024/25.
|
93. |
Quarterly Waivers Report PDF 555 KB
To consider the report of the Strategic
Director for Corporate Resources.
Minutes:
The Procurement Manager
presented the Quarterly Waivers Report, making the following
points:
- this had been a
recommendation from both the external and internal
audit;
- it was typical for
this to be reported quarterly or every six months within Local
Authority;
- since staff training
had begun there had been a reduction in the number of
waivers;
- a number
of breaches were due to grants from central
government;
- there had been no
deliberate breaches; and
- it was normal for
there to be a lot of breaches.
The Strategic Director for
Corporate Resources provided context for a
breach regarding CCTV and advised that it had
been necessary for the function of CCTV in the City Centre to use
the same supplier.
The Procurement Manager, and
the Strategic Director for Corporate Resources answered
Members’ questions in the following
terms:
- tenders in
excess of £100,000 had to be signed off by the
Procurement Team, which involved a rigorous
process;
- some direct awards
were through framework with another organisation, such as a
contract for Trews Weir with the Environment
Agency;
- a grant had been
given by MCHLG, which required a short-term
waiver;
- Portfolio Holders
were involved in approving and signing off waivers over
£215,000.
The Audit and Governance Committee noted the
Quarterly Waivers Report.
|