Issue - decisions

Topsham Flood Defence Funding Roger Crane

19/11/2015 - Topsham Flood Alleviation Measures

Agreed

 

 

That Council approve the underwriting up to £15,000 of the cost of Scheme 2: Ferry Road South, described in paragraph 8.4 of the circulated report to enable the works to be commenced during the current financial year.  This amount to be conditional upon suitable guarantees from the Topsham Emergency Group being in place for the repayment of the money.

 

Reason for Decision:

 

As set out in the report.