Public Sector Decarbonisation Scheme 3b Project – RAMM & Riverside Leisure Centre

03/10/2024 - Public Sector Decarbonisation Scheme 3b Project – RAMM & Riverside Leisure Centre

Agreed:

 

RECOMMENDED that Council approve:-

 

(1) for the PSDS 3b project (RAMM & Riverside) not proceed any further, following consideration of the outcomes of the Year 1 exploration, design, and pricing stages; and

(2) for Officers to allocate time to progress matters in preparation for future funding opportunities to secure monies required to decarbonise both sites.

 