To consider the report to not proceed with the Public Sector Decarbonisation Scheme Project and to not draw down any further grant funding from the funder (Salix) to avoid additional costs for an undeliverable project.
Decision type: Key
Reason Key: Significant expenditure or saving & affects > 1 ward;
Decision status: For Determination
Wards affected: (All Wards);
Notice of proposed decision first published: 25/07/2024
Work Programme: Performance Review / Best Value;
Decision due: 1 Oct 2024 by Executive
Lead member: Portfolio Holder for Climate, Ecological Change and Communities
Lead director: Strategic Director for Place
Contact: Jo Pearce, Net Zero Project Manager Email: jo.pearce@exeter.gov.uk.